You will need
  • - sliding gates;
  • level;
  • roulette;
  • - shovel;
  • master - cord;
  • cement, sand, water;
  • - steel channel 20 and the valve 12;
  • - screwdriver;
  • - the drill.
Instruction
1
Before installing a sliding gate, check whether the opening in the fence requirements. Measure the length of the fence to one side of the future gate – size area free of trees and other obstacles must be not less than one and a half times longer than the width of the opening. Please note: there should be no bias, turns the fence, etc.
2
Make the layout of the concrete base. To do this, along the fence, starting from the edge of the opening in the side of the rollback, set aside a distance equal to half of the opening in the fence. The width of the pit should be 400-500 mm deep areas. From the opposite side, mark a hole for the support post to set the post does not interfere with the travel and not Sauzal opening. Dig a hole so that it was with a depth of at least 200 mm deeper than the layer of soil freezing.
3
Take the channel 20 and the rebar diameter 12, weld pieces of rebar to the base of the channel so as to obtain double "comb". Then, reinforce the design of the transverse relationship of the rebar.
4
Lower resulting core into the hole and channel up so that it was parallel to the fence and horizontally, the lateral surface should adjoin the existing fence post. Note: from what height you place the Foundation element will depend on the clearance from the bottom edge of the gate to the road.
5
Fill the pit with concrete so that the surface of the channel was not closed. Leave to dry for not less than 6 days.
6
Indicate the line of movement of the gate with the master cord at the height of 150-200 mm. Prepare for installation of the roller truck. Draw line position of roller bearings.
7
Collect prepared roller trolley by inserting them inside of the carrier profile. Guide the installation of sliding doors and horizontal adjustment of the shield. Install the end clip and the cover support profile.
8
Then install the upper guide, Kronlein, and the side with holes for fasteners must be directed toward the support post. Close to the fence post put a reply post to his ribs in the closed position, the closed front gate.
9
Installation guide traps and automation, if it is provided by the design of the gate.