You will need
  • - primer;
  • - roller;
  • water;
  • - cement;
  • - sand;
  • construction mixer;
  • - trowel;
  • rule;
  • Board;
  • - screws;
  • level.
Instruction
1
Note: for walls from foam concrete it is important that saved it was the right balance of internal and external plaster. In addition, under the outer layer of plaster and the wall should not accumulate moisture, in other words, the wall needs to "breathe". If you do not provide all of these conditions, the constant freezing of water and thawing in the outer layer will crack, while the inner mold.
2
Plaster should not be too thick: the optimum thickness of the outer layer is from 5 to 10 mm, and the inner layer is 10-20 mm. Plaster itself dries for a long time, so to speed up this process, make sure that the temperature in the room where the finishing work was varied in the range from 5 to 30 degrees (not below this level).
3
Before applying plaster, be sure to treat the wall: for this programsuite surface. After this prepare the solution: mix one part cement with three parts sand and water, and after all these components mix well with a mixer.
4
Using a spatula, apply the solution on the walls, though easier to apply the slap method: to do this, take the left hand grater, which put the prepared mixture, and the sharp motion, throw the solution on pre-moistened with water wall. After complete the grout the entire surface, smooth circular movements of the trowel to smooth the deposited layer, adding with a spatula in the empty space with cement mortar.
5
To make a flat corner, attach using screws or other fasteners Board (set the Board on the level). Stukatura the wall along the boards, and after a layer dries, remove the Board.