You will need
  • The time sheet
Instruction
1
To calculate the number of man-days, you need to first calculate the increased "man-hours". To do this, for each employee multiplied by the number of hours worked per day by the number of days in the month.
2
Then sum up all the resulting works. The resulting figure will be the "person-hours".
3
Then the resulting number is divided by 8 hours (number of hours per day according to TK the Russian Federation). The resulting figure will be an indicator of "man-days".